Wednesday, May 25, 2011

Tutorial 4









We did the AON for our project. It gives us a clearer picture of the datelines and duration for each task given. However, it's quite confusing in the calculations and predecessors.

We did the Gantt chart using Microsoft Project. It is quite complicated to use using this software though. I would prefer drawing it out on a paper.

Wednesday, May 18, 2011

Tutorial 3 - Mind mapping






Reflection:
The mindmeister website is useful, neat and easy to use for mind mapping.

Sunday, May 15, 2011

Tutorial 2

Estimated duration – 3days, 12pm – 7pm

Estimated cost - $11000 (total)

Place rental - $60 per day for each booth

Products - $5000 (refreshment stall)

$3000 (beach wears stall)

$500 (game stalls)

$2000(souvenir stall)

Layout - $200

Responsibility matrix - Marketing (publicity, prepare layout of the booth)

Finance

Resource (manage manpower, products, rental)

Current Issue - Weather, number of people visiting sentosa that time

Man power requirement – 2 sale assistant per stall

Resource requirement - 2 fridges, 5 booths, products (snacks, drinks, beach wears, keychains, mugs, balloons and tins for games)