Wednesday, May 25, 2011
Tutorial 4
We did the AON for our project. It gives us a clearer picture of the datelines and duration for each task given. However, it's quite confusing in the calculations and predecessors.
We did the Gantt chart using Microsoft Project. It is quite complicated to use using this software though. I would prefer drawing it out on a paper.
Wednesday, May 18, 2011
Sunday, May 15, 2011
Tutorial 2
Estimated duration – 3days, 12pm – 7pm
Estimated cost - $11000 (total)
Place rental - $60 per day for each booth
Products - $5000 (refreshment stall)
$3000 (beach wears stall)
$500 (game stalls)
$2000(souvenir stall)
Layout - $200
Responsibility matrix - Marketing (publicity, prepare layout of the booth)
Finance
Resource (manage manpower, products, rental)
Current Issue - Weather, number of people visiting sentosa that time
Man power requirement – 2 sale assistant per stall
Resource requirement - 2 fridges, 5 booths, products (snacks, drinks, beach wears, keychains, mugs, balloons and tins for games)